#1 Posted : 31 August 2003 19:14:00(UTC)
Rank: Guest
Admin

Posted By Peter Burnett
Recently I was told by site agent whose company told him that there was no requirement to notify the HSE of a CDM project if it did not exceed a 30,000 pounds budget.

I have little experience of this area but am aware the requirements to do so if lasts 30+ days etc,etc but never heard baised on monetary value. Your replies would be appreciated.
Admin  
#2 Posted : 31 August 2003 21:48:00(UTC)
Rank: Guest
Admin

Posted By Paul Craythorne
Peter,

An extract from the statutory instrument

(4) For the purposes of these Regulations, a project is notifiable if the construction phase:
(a) will be longer than 30 days; or
(b) will involve more than 500 person days of construction work,
and the expression "notifiable" shall be construed accordingly.

No mention of £30,000

Hope this clarifies the situation.

Regards,

Paul Craythorne
Admin  
#3 Posted : 03 September 2003 09:33:00(UTC)
Rank: Guest
Admin

Posted By Graham Findlay
The site agent is talking rubbish. There is no cost ceiling that decides whether a project is notifiable or not. It is down to the duration of the work on site.

Graham
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.