Sorry chaps more advice needed.
The Principal Contractor finishes his involvemernt in the project, and some weeks later, we revisit site to continue with our works, possibly lasting 2 months. Effectively we are the only guys on site, it involves CDM activities, but no mention in the contract about the PC role. The update to the F10 is easy enough but does the client have to "re appoint" a PC?
|
|
|
|
|
|
Rank: Guest
|
Posted By Ron Hunter
You include the word "continue" (your work).
I guess then that your work was suspended for the duration of the Notified Project. (The PC has gone, so I guess he wasn't paying your wages!)
All construction work is covered by CDM, but does your (presumably seperate) bit meet the notification thresholds? If not, no F10, no PC.
|
|
|
|
|
|
Rank: Guest
|
Posted By Robert K Lewis
Just to end Ron's answer
If yes then you are it subject to client appointment. CDMC must also be around somwwhere.
Bob
|
|
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.