Quick question, am I right in assuming that it is the Principal Contracor who produces a Construction Phase Plan for notifiable projects. CDM C would review / advise client??
Thanks
|
|
|
|
Rank: Super forum user
|
|
|
|
|
Rank: Super forum user
|
Remember though the legal duty (Regulation 16) to ensure the Project does not proceed to the Construction Phase unless the Plan is adequate rests with the Client.
|
|
|
|
Rank: Super forum user
|
Duty of CDM-C to advise the client the CPP is sufficiently prepared etc. etc.
The client does not have to see the CPP. That's what he appoints the CDM-C to do.